Taloja Mass Housing power supply

CIDCO · Taloja, Sectors 21, 22, 27 and 29

Back to Portfolio

Scope of work

CIDCO awarded us the power supply package for its Mass Housing Scheme in Sectors 21, 22, 27 and 29 at Taloja.

  • We developed the 33/11 kV distribution substation in Sector 1B, Taloja Phase II, including three 10/12.5 MVA transformers, and connected feeders for the four housing sectors.
  • We supplied and installed 33 kV gas-insulated switchgear with two incoming sections, one bus coupler and three outgoing sections.
  • We supplied and installed 11 kV vacuum circuit-breaker panels with three incoming sections, two bus couplers and twelve outgoing sections.
  • We laid 3.8 km of 33 kV cable and 21.47 km of 11 kV cable, complete with straight-through joints, terminations and protective ducting. We also connected ring main units to local transformers.

Project photos

Select a photo to enlarge

Substation exterior and surrounding housing
Outdoor transformer equipment beside the substation
Switchgear lineup in the substation room
Open switchgear cubicles during installation
Work across the switchgear lineup
Operating the switchgear controls
Close-up of switchgear controls